Discover more about the Robbins Neurosciences Lab, a project managed by the Department of Campus Planning & Facilities Management at ÐÇ¿Õ´«Ã½.
Project Information
- Location: Main campus
- Client: School of Medicine
- Scope: New neurosciences lab on the seventh floor of the Robbins Building
- Total project area: 24,390 gross square feet
- The project renovated ~75% of the seventh floor to create a transformative space that is highly functional and supports collaboration and shared resources. In turn, this will help attract new principal investigators elevating the Department of Neurosciences and ÐÇ¿Õ´«Ã½ as a whole.
Schedule:
- Design: Sept. 2019—Feb. 2020
- Construction: March 2022—Aug. 2023
- Beneficial Occupancy Date (BOD): Aug. 22, 2023
Financials:
- Budget: $9.2 million
- Total project cost: $8.1 million